Kurt Ehmann's EP

posted May 24, 2016, 2:22 PM by Greg Ehmann   [ updated Aug 10, 2016, 1:01 PM ]
For my Eagle project we will be building a foot bridge over a small creek at Sabatino Park in Sleepy Hollow.  This project will take two days to complete.

May 28th

Begin at 8am, end when forms are complete 

  • Clear site of brush

  • Dig post holes

  • Frame forms for concrete

  • Install Rebar


Tools required:

  Hand clippers, loppers, hand saws, shovels, post hole diggers, work gloves, wheelbarrows


June 8th

Begin at 9am , end when concrete is complete

  • Pour concrete (10am Ozinga Ready Mix Concrete)

June 10th

Begin at 1:30pm , end when poles installed

  • Install poles (SH Public Works)

June 11th

Begin at 8am , end when bridge is complete

  • Install telephone poles

  • Attach decking

  • Build railings


Tools required:

  Drills, work gloves

   

Breakfast and lunch will be provided both Saturdays.

A very big thank you to all the people and businesses who helped make this project possible:

Ozinga Ready Mix Concrete - John Holzl
Sleepy Hollow Service Club
Limitless Design and Construction - Joe Minaglia
Meng Remodeling - Hans Meng
Home Depot - Carpentersville and Elgin
Village of Sleepy Hollow Public Works
The Village of Sleepy Hollow
Welch Brothers INC