For my Eagle project we will be building a foot bridge over a small creek at Sabatino Park in Sleepy Hollow. This project will take two days to complete.May 28th

Begin at 8am, end when forms are complete

    • Clear site of brush

    • Dig post holes

    • Frame forms for concrete

    • Install Rebar

Tools required:

Hand clippers, loppers, hand saws, shovels, post hole diggers, work gloves, wheelbarrows

June 8th

Begin at 9am , end when concrete is complete

    • Pour concrete (10am Ozinga Ready Mix Concrete)

June 10th

Begin at 1:30pm , end when poles installed

    • Install poles (SH Public Works)

June 11th

Begin at 8am , end when bridge is complete

    • Install telephone poles

    • Attach decking

    • Build railings

Tools required:

Drills, work gloves

Breakfast and lunch will be provided both Saturdays.

A very big thank you to all the people and businesses who helped make this project possible:

Ozinga Ready Mix Concrete - John Holzl

Sleepy Hollow Service Club

Limitless Design and Construction - Joe Minaglia

Meng Remodeling - Hans Meng

Home Depot - Carpentersville and Elgin

Village of Sleepy Hollow Public Works

The Village of Sleepy Hollow

Welch Brothers INC

Pictures

Day 1 Video